Estimation and Costing Study Material for SSC Junior Engineer (Civil Engineering) Exam PDF - CivilEnggForAll Exclusive

Civil-Engineering-For-All

CONTENTS

  • Definition of Estimation and Costing
  • Lumpsum
  • Measurement of Materials and Works
  • Types of Estimates
  • Abstract of Estimate Form
  • Data
  • Analysis of Rates
  • Detailed Specifications
  • Concrete in Foundations
  • Cement Concrete
  • Introduction, Necessity of  Valuation of Building

DEFINITION OF ESTIMATION AND COSTING 

  1. Estimating is the technique of calculating or  Computing the various quantities and the expected  Expenditure to be incurred on a particular work or  project. 
  2. Particularly if the funds available are less than the  estimated cost the work is done in part or by reducing  it or specifications are altered, the following  requirement are necessary for preparing an  estimate. 
  3. Drawings like plan, elevation and sections of  important points. 
  4. Detailed specifications about workmanship &  properties of materials etc. 
  5. Standard schedule of rates of the current year. 

REQUIREMENT FOR ESTIMATION AND COSTING 

  1. Estimate give an idea of the cost of the work and  hence its feasibility can be determined i..e whether  the project could be taken up with in the funds  available or not. 
  2. Estimate gives an idea of time required for the  completion of the work. 
  3. Estimate is required to invite the tenders and  Quotations and to arrange contract. 
  4. Estimate is also required to control the expenditure  during the execution of work. 
  5. Estimate decides whether the proposed plan  matches the funds available or not. 

ESTIMATION AND COSTING STUDY MATERIAL FOR RRB JE EXAM PDF: CLICK HERE

METHOD OF ESTIMATING

Estimating involves the following operations 

  1. Preparing detailed Estimate. 
  2. Calculating the rate of each unit of work 
  3. Preparing abstract of estimate 

DATA REQUIRED TO PREPARE AN ESTIMATE 

  1. Drawings i.e., plans, elevations, sections etc. 
  2. Specifications. 
  3. Rates. 

Drawings 

If the drawings are not clear and without complete  dimensions the preparation of estimation become very  difficult. So, It is very essential before preparing an  estimate. 

Specifications 

  • General Specifications: This gives the  nature, quality, class and work and materials  in general terms to be used in various parts  of woks. It helps to form a general idea of  building. 
  • Detailed Specifications: These gives the detailed  description of the various items of work laying down  the Quantities and qualities of materials, their  proportions, the method of preparation  workmanship and execution of work. 

Rates 

For preparing the estimate the unit rates of each item  of work are required. 

  1. For arriving at the unit rates of each item. 
  2. The rates of various materials to be used in the  construction. 
  3. The cost of transport materials. 
  4. The wages of labour, skilled or unskilled of masons,  carpenters, Mazdoor, etc., 

IES MASTER CIVIL ENGINEERING GATE STUDY MATERIALS PDF: CLICK HERE

COMPLETE ESTIMATE

Most of people think that the estimate of a structure  includes cost of land, cost of materials and labour, But  many other direct and indirect costs included and is  shown below.

Complete Estimate

LUMPSUM 

While preparing an estimate, it is not possible to  workout in detail in case of petty items. Items other  than civil engineering such items are called lumpsum  items or simply L.S.Items.  The following are some of L.S. Items in the estimate. 

  1. Water supply and sanitary arrangements. 
  2. Electrical installations like meter, motor, etc., 
  3. Architectural features. 
  4. Contingencies and unforeseen items. 

In general, certain percentage on the cost of estimation  is alloted for the above L.S.Items  Even if sub-estimates prepared or at the end of  execution of work, the actual cost should not exceed  the L.S.amounts provided in the main estimate. 

WORK CHARGED ESTABLISHMENT: 

During the construction of a project considerable  number of skilled supervisors, work assistance, watch  men etc., are employed on temporary basis. The  salaries of these persons are drawn from the L.S.  amount allotted towards the work charged  establishment. that is, establishment which is charged  directly to work. an L.S.amount of 1½ to 2% of the  estimated cost is provided towards the work charged  establishment. 

MEASUREMENT OF MATERIALS AND  WORKS  UNITS OF MEASUREMENTS 

The units of measurements are mainly categorised  for their nature, shape and size and for making  payments to the contractor and also. The principle of  units of measurements normally consists the following: 

  • Single units work like doors, windows, trusses etc.,  are expressed in numbers. 
  • Works consists linear measurements involve length  like cornice, fencing, hand rail, bands of specified  width etc., are expressed in running metres (RM) 
  • Works consists areal surface measurements involve  area like plastering, white washing, partitions of  specified thickness etc., are expressed in square  meters (m2) 
  • Works consists cubical contents which involve  volume like earth work, cement concrete, Masonry  etc are expressed in Cubic metres.

RULES FOR MEASUREMENT

The rules for measurement of each item are invaribly  described in IS-1200. However some of the general  rules are listed below. 

  1. Measurement shall be made for finished item of  work and description of each item shall include  materials, transport, labour, fabrication tools and  plant and all types of overheads for finishing the  work in required shape, size and specification. 
  2. In booking, the order shall be in sequence of length,  breadth and height or thickness. 
  3. All works shall be measured subject to the following  tolerances. 
    1. Linear measurement shall be measured to the  nearest 0.01m. 
    2. Areas shall be measured to the nearest 0.01 sq.m 
    3. Cubic contents shall be worked-out to the  nearest 0.01 cum 
  4. Same type of work under different conditions and  nature shall be measured separately under  separate items. 
  5. The bill of quantities shall fully describe the  materials, proportions, workmanships and  accurately represent the work to be executed.  6. In case of masonary (stone or brick) or structural  concrete, the categories shall be measured  separately and the heights shall be described: 
    1. from foundation to plinth level  
    2. from plinth level to First floor level 
    3. from Fist floor to Second floor level and so on.

ACE ACADEMY CIVIL ENGINEERING GATE STUDY MATERIALS PDF: CLICK HERE

METHODS OF TAKING OUT QUANTITIES

The quantities like earth work, foundation concrete,  brickwork in plinth and super structure etc., canbe  workout by any of following two methods: 

  • Long wall – short wall method 
  • Centre line method. 
  • Partly centre line and short wall method.

Long wall-short wall method

In this method, the wall along the length of room  is considered to be long wall while the wall  perpendicular to long wall is said to be short wall.  To get the length of long wall or short wall, calculate  first the centre line lengths of individual walls. Then  the length of long wall, (out to out) may be  calculated after adding half breadth at each end to  its centre line length. Thus the length of short wall  measured into in and may be found by deducting  half breadth from its centre line length at each  end. The length of long wall usually decreases from  earth work to brick work in super structure while  the short wall increases. These lengths are  multiplied by breadth and depth to get quantities. 

Centre line method

This method is suitable for walls of similar cross  sections. Here the total centre line length is  multiplied by breadth and depth of respective item  to get the total quantity at a time. When cross walls  or partitions or verandah walls join with mainhall,  the centre line length gets reduced by half of  breadth for each junction. such junction or joints  are studied caefully while calculating total centre  line length.The estimates prepared by this method  are most accurate and quick. 

Partly centre line and partly cross wall method

This method is adopted when external (i.e., allround  the building) wall is of one thickness and the internal  walls having different thicknesses. In such cases,  centre line method is applied to external walls and  long wall-short wall method is used to internal  walls. This method suits for different thicknesses  walls and different level of foundations. Because of  this reason, all Engineering departments are  practicing this method.

DETAILED ESTIMATE 

The preparation of detailed estimate consists of working  out quantities of various items of work and then  determine the cost of each item. This is prepared in  two stages. 

Details of measurements and calculation of  quantities

The complete work is divided into various items  of work such as earth work concreting, brick work,  R.C.C. Plastering etc., The details of  measurements are taken from drawings and  entered in respective columns of prescribed  proforma. the quantities are calculated by  multiplying the values that are in numbers  column to Depth column as shown below:

Details of Measurement form

Abstract of Estimated Cost

The cost of each item of work is worked out from  the quantities that already computed in the details  measurement form at workable rate. But the total  cost is worked out in the prescribed form is known  as abstract of estimated form. 4% of estimated Cost  is allowed for Petty Supervision, contingencies and  Unforeseen items.

Abstract of Estimated Cost

The detailed estimate should accompanined with 

  • Report 
  • Specification 
  • Drawings (plans, elevation, sections) 
  • Design charts and calculations 
  • Standard schedule of rates.

METHODS OF PREPARATION OF APPROXIMATE  ESTIMATE

Preliminary or approximate estimate is required for  studies of various aspects of work of project and for its  administrative approval. It can decide, in case of  commercial projects, whether the net income earned  justifies the amount invested or not. The approximate  estimate is prepared from the practical knowledge and  cost of similar works. The estimate is accompanied by  a report duely explaining necessity and utility of the  project and with a site or layout plan. A percentage 5 to  10% is allowed for contingencies. The following are the  methods used for preparation of approximate estimates. 

  • Plinth area method 
  • Cubical contents methods  
  • Unit base method. 

MADE EASY CIVIL ENGINEERING GATE NOTES PDF: CLICK HERE

Plinth area method

The cost of construction is  determined by multiplying plinth area with plinth  area rate. The area is obtained by multiplying  length and breadth (outer dimensions of building).  In fixing the plinth area rate, carefull observation  and necessary enquiries are made in respect of  quality and quantity aspect of materials and  labour, type of foundation, height of building, roof,  wood work, fixtures, number of storeys etc.,  As per IS 3861-1966, the following areas include  while calculating the plinth area of building. 

  • Area of walls at floor level. 
  • Internal shafts of sanitary installations not  exceeding 2.0m2, lifts, airconditioning ducts etc., 
  • Area of barsati at terrace level:  Barsati means any covered space open on one  side constructed on one side constructed on  terraced roof which is used as shelter during  rainy season. 
  • Porches of non cantilever type. 

Areas which are not to include

  • Area of lofts. 
  • Unenclosed balconies.  
  • Architectural bands, cornices etc., 
  • Domes, towers projecting above terrace level. 
  • Box louvers and vertical sunbreakers.

Cubical Contents Method

This method is  generally used for multistoreyed buildings. It is  more accurate that the other two methods viz.,  plinth area method and unit base method. The  cost of a structure is calculated approximately as  the total cubical contents (Volume of buildings)  multiplied by Local Cubic Rate. The volume of  building is obtained by Length x breadth x depth  or height. The length and breadth are measured  out to out of walls excluding the plinth off set.  The cost of string course, cornice, carbelling etc.,  is neglected.  The cost of building = volume of buildings x  rate/ unit volume. 

Unit Base Method

According to this method  the cost of structure is determined by multiplying  the total number of units with unit rate of each  item. In case schools and colleges, the unit  considered to be as ‘one student’ and in case of  hospital, the unit is ‘one bed’. the unit rate is  calculated by dividing the actual expenditure incurred or cost of similar building in the nearby locality by the number of units.

ESTIMATION AND COSTING STUDY MATERIAL FOR SSC JE PDF CIVILENGGFORALL

DOWNLOAD LINK : CLICK HERE

PASSWORD : CivilEnggForAll

OTHER USEFUL BOOKS

  • facebook
  • googleplus
  • twitter
  • linkedin
  • linkedin
  • linkedin
Previous «
Next »

Leave a Reply

Your email address will not be published. Required fields are marked *

DO FOLLOW OUR FACEBOOK PAGE

PARTNER MOBILE APP